Experience Recored for Soil Improvement
Year Project Location ( Egypt ) Client
Main Contractor
Consultants
Architect
Engineers
Contract Value (LE) Duration (Month) Treatm
Depth
(m)
Treatm.
Volume
(m3)
Soil Condition Using Technique Remarks
1981 Menouf Substation Menouf E.E.A. - 600,000 3 20 - Fill & soft Clay Stone
columns
1984 Safaga Grain
Silos
Safaga Red Sea Ports Authority - 450,000 6 12 - Fill & loose Sand Vibro Compaction
2006 Port Ghalib - Phase II Marsa
Allam
EMAK - 6,000,000 5 12 - Soft Clay Stone
columns
2010 Marassi Sidi Abdel Rahman North Coast North Coast Marassi Matrouh Eamaar Misr TCI Turner 40,000,000 5 6 to 12 - Fill & soft Clay Displacement mini-piles
                       
                       
                       
                       
                       
 