Project: Secon tower

Location: Cairo                        

Client: Arabtec – Siac JV

Year of construction: 2013

Budget: 68,5,000 EGP

Project description

The biggest largest project in year 2013 at Cornish EL-Nile -maadi

 Scope of work:

  • 1-Bored piles works
    • About 704 no. of Bored piles with diameter 100cm and depth 26m
    • About 409 no. of Bored piles with diameter 80cm and depth 26m

       

       

  • 2-Construct of about 11,400m2 of diaphragm wall with thickness 80 cm and depth 30m to deep excavationup to 13m deep

     

     

  • 3-Post grouted ground anchors:

        1st row above ground water table about 117 no. of anchors

        2nd row below ground water table about 170 no. of anchors

     

  • 4-Ground water control by usinghorizontal grout Blanket (soft jell)to about 9,000m2

     

  • 5-Pile load test on piles up to 1440 ton

 

 

 

 