Name of Project: West Damietta Simple Cycle Power plant

Location: Damietta– Egypt

Client: Kharafi national

Consultant: PGESCO

Year of construction: 2012

Budget: 20,837,600 EGP

Project description:

The proposed site for the power plant is located at Damietta. The plant project main structures are the turbine pedestal, the transformers, generator transformers and tanks (solar, service water, etc. ….) in addition, the plant project include many other structure such as firefighting building , control building etc.

       Pilling works:

  • 22,000 linear meter of piles with diameter 800/1000 mm , length 36 meter
 