Project: Assuit Barrage

Location: Assuit

Client: Egyptian French JV for new Assuit Barrage (Vinci - Arabco- Orascom)

Year of construction: 2012-2016

Budget: 85,500,000 EG.P

Scope of work:

  • Supply & Construction of Single phase cut off wall for ring dam ( SPW ) ( Nov 2010- March 2013)
  • Construction of permanent Double Phase cut off wall ( DWP) underneath the new barrage
  • Construction of Diaphragm wall as foundation for barrage pier( s) ( July 2013- Dec 2013 )
  • Installation of Deep wells for dewatering( Feb 2103- June 2013 )
  • Construction of Permanent cut of wall for diversion canal( Mid 2016 )

Cutoff Wall Works:                                     

Construct of cutoff walls and with thickness from 80 cm to 100 cm. Depth of walls is up to 40 meter. Total quantity of executed diaphragm wall is 24,260 square meter

 

 

 

 