Home | Bauer Group |
 
 
Agamy sewage PS 04
Amiria shaft
Sayphon under suez canal
Sokhna power palnt
TBM rescue shaft
 
Sokhna power palnt

Project :  Alsokhna supercritical thermal power plant

Location: El- ain Elsokhna

Client: Consortium of Consolidated contractors group and hassan allam sons.

Consultant: A&A Engineers and Consultants

Year of construction: 2010

Budget: 7,773,300 LE

Scope of work :       

  • 1-Diaphragm Wall works:

Construct a circular shaft Diamter 75 meter , thickness (100 cm), & (30 ) meter deep. The total quantity of diaphragm wall is (7,280 square meter).

 

Copy Right©2015 Bauer Egypt.  All rights reserved >